INTRODUCTION
Boretech were engaged to provide wet hire of 3,4 large vacuum Trucks on the Yanchep Rail Line Extension covering the construction works from Yanchep to Alkimos.
EQUIPMENT
• 8,000l STG Global
• 6,000l Vermeer
• 6,000l Vacudig
• 4,500l Vermeer
GROUND CONDITIONS
Sand & Limestone
CHALLENGES
The work involved long shifts with all crews working 6 days per week. This is a challenge which we embrace but we need to manage risk. To monitor fatigue management we implemented crews that altered their roster. Sections of the work required Night Shift which required extensive planning.
TEAM SUCCESS
We have been very proud of our crew, all working together and looking out for each other on the job.
DURATION
Ongoing
DATE COMMENCED
May 2023
