INTRODUCTION
Boretech were awarded the Electrical HDD package on the Metronet as part of the Mandurah Train Station Upgrade.
SCOPE
6 x DN160mm Power x 142m
EQUIPMENT
D24x40
GROUND CONDITIONS
Limestone
CHALLENGES
• Keeping crews fully operational during the COVID-19 pandemic.
• Working to strict traffic scenarios to ensure no disruption to the public whilst working around the active Train & Bus station.
• A lot of planning was required to pick the correct spot to string out lengths for welding without disrupting pedestrians and buses.
TEAM SUCCESS
To ensure maximum production and to meet the clients deadlines our crew stayed in Mandurah for the duration of the job. This was greatly appreciated and showed their dedication to the job.
DURATION
1.5 weeks
DATE COMPLETED
January, 2021