Alfred and Narla Road, Swanbourne


INTRODUCTION

Boretech was contracted by a new valued client to assist with HDD works at Alfred and Narla Road, Swanbourne.

SCOPE

Boretech was contracted to Install DN400mm HDPE pipe in two separate locations over a distance of 110m and 70m respectively.

EQUIPMENT
  • BT 53 Vermeer 40x55DR drill
  • BT 63 Kubota 5.5T Excavator U55-4
  • BT 90 STG VAC TRUCK HDV8000
  • BT 134 STG 8000 Ltr Vac Truck
  • BT 135 MAN Drill truck with 8000ltr Truck mounted Mud Mixing System
  • BT 132 Triaxle trailer
  • BT 50 Hilux Light Vehicle
  • BT 145 DigiTrack DCI F5 Sonde & Tracking System
  • BT 199 DCI TeraTrak Bore profile enabling machine
GROUND CONDITIONS

Running white dry beach sands.

CHALLENGES

The team were required to efficiently deliver these works in a short time frame, working with both the client, school and golf club requirements to keep all disruptions to a minimum.

The terrain was also a challenge with the approximate elevation difference between entry and exit being 25m across shot two, also in an environmentally sensitive area.

The ground being drilled was a very dry white beach sand, that the Drill crew were able to combat with good advice from our Mud engineer.

TEAM SUCCESS

Initial success was achieved by using the DCI TeraTrack topographical-mapping tool that allowed us to design a Bore plan before mobilizing the crew and equipment. This gave both the Boretech Crew and Management team confidence in the works from the first day onsite.

The First drill shot was successfully completed under the anticipated time allocated and gave the team an appreciation of the ground conditions. It was also good to see our new Driller Jason stepping up and assisting the client with great communication & instructions for the pipe handling on pullback.

The second drill shot was also delivered within its anticipated time frame, including a minor mechanical issue that the crews solved efficiently.

Boretech scheduled extra workers and Vac trucks to assist during these works to mitigate any delays.

It was great to see the teamwork between not only the Boretech crew but also between Boretech and our client.

DURATION

8 days onsite

DATE COMPLETED

May, 2025

ABN 68 623 214 497 | ACN 623 214 497

Licenses

EC Licence 14748
Worksafe Restricted Asbestos Licence WR2407