Boretech were proudly engaged to undertake section 2 & 3 of its reticulation upgrade on Belmont Avenue. The job consisted of boring a new main line 110m & 40mm PVC along one side of the road and various pipe sizes on the other side of the road right up to Great Eastern Highway.
EQUIPMENT
DitchWitch 20/20 & DitchWitch 922
GROUND CONDITIONS
Sand
CHALLENGES
• Tight access with busy roads requiring traffic management throughout
• Extensive locating required to capture all underground services
TEAM SUCCESS
Despite busy traffic, our team remained incredibly calm & focused throughout the duration of the project.